First-time buyers usually underestimate two things: how long tooling takes, and how early certification has to be booked. Here is the full sequence, in the order it has to happen.

The nine steps, in order
1 Brief & specCategory, market, volumes, branding, standard
2 Platform choiceExisting shell or a new mold
3 Quote & toolingWho owns the mold, exclusivity, exit terms
4 2D / 3D reviewGraphics, vents, accessory points
5 Tooling & T1First shots, iterate on fit and finish
6 Lab testingBook the slot before the sample is perfect
7 PP approvalProduction materials, production line
8 Mass productionInline QC plus pre-shipment inspection
9 Docs & shippingCI, packing list, conformity file
Steps 6 and 7 cause most first-order delays: a lab slot booked too late, and artwork changed after the PP sample was signed off.

1. Brief and specification

Category, target market, target retail price, volumes, sizes, colors, branding, packaging and the certification standard required. Vague briefs produce vague quotes.

2. Construction and platform selection

Choose an existing platform or commit to a new mold. Reusing an existing shell is dramatically cheaper and faster - often the single biggest decision in the project.

3. Quotation and tooling decision

Tooling is quoted separately. Confirm who owns the mold, whether it is exclusive to you, and what happens to it if the relationship ends. Get this in writing.

4. 2D artwork and 3D review

Graphics, logo placement, vent layout, accessory points. This is the cheapest stage to change your mind, so be difficult here rather than later.

5. Tooling and T1 samples

The mold is cut and the first shots are pulled. Expect to iterate - T1 samples rarely match the 3D render exactly on fit and finish.

6. Laboratory testing

This is the step that catches people out. Lab slots are booked, not on-demand, and a failed test means a design change plus a re-test. Book the lab as soon as the sample exists, not after the samples look perfect.

7. PP sample approval

Pre-production samples made on the actual production line, with production materials. What you sign off here is what you get. Check the buckle, the strap length, the liner fit and the artwork position - not just the color.

8. Mass production and inspection

Production run, inline QC, and a pre-shipment inspection. Agree the AQL level before production starts, not after you find defects.

9. Documentation and shipping

Commercial invoice, packing list, and whatever conformity documentation your market requires. For the EU this includes the technical file; for the US, the CPSC requirements. Ask who prepares it and who signs it.

The two delays that hit almost everyone

One: booking the test lab late, then discovering a failure. Two: changing artwork after the PP sample was approved. Both are avoidable, and both are schedule problems rather than manufacturing problems.

If you are planning a programme and want a realistic sequence for your market, send us the brief - we will come back with what is achievable and what has to be rescheduled.